TITLE 4. THE PHILADELPHIA BUILDING CONSTRUCTION AND OCCUPANCY CODE
SUBCODE "B" (THE PHILADELPHIA BUILDING CODE)
SECTION B-3302.0 CONSTRUCTION DOCUMENTS AND SPECIAL PERMITS.
B-3302.1 Temporary construction: Before any construction
operation is started, construction documents shall be filed with the code
official showing the design and construction of all sidewalk sheds, temporary
vehicular passageways, trestles, footbridges, guard fences, [and] other similar
devices required in the operation and any locations where waste materials will
be disposed.
[18]
* * *
B-3302.4 Duration: Temporary construction, scaffolding, or
encroachments shall be removed from a construction site after the final
inspection is made by the Department or within 30 days after the fulfillment of
the requirements of the permit.
* * *
B-3304.3 Sidewalk bridge: Wherever the ground is excavated
under the sidewalk, a sidewalk bridge shall be constructed at least 4 feet (1219
mm) wide, or a protected walkway of equal width shall be erected in the street,
provided that the required permit for such walkway is obtained from the
[administrative authority] Streets Department.
B-3304.4 Sidewalk shed:
Sidewalk sheds shall be as provided for in accordance with Sections B-3304.4.1
through B-3304.4.4 except where sidewalks are closed [by the authority having
jurisdiction] with approval of the Streets Department.
* * *
B-3305.4 Hot work operations: Construction which includes
cutting, welding or brazing operations shall be in accordance with the
requirements of the fire prevention code.
* * *
B-3308.2 Drainage: Sitework associated with construction
activity for which a building permit is required, shall not result in the
concentration of surface water drainage to adjoining properly.
Exception:
Where terrain slopes toward a natural water course such as a creek, stream or
river.
* * *
B-3309.2 Chimney, soil and vent stacks: Wherever a new
building or structure is erected to greater or lesser heights than an adjoining
building, the construction and extension of new or existing chimneys shall
conform to the provisions of the mechanical code, and the construction and
extension of soil and vent stacks [and the location of window openings] shall
comply with the [provisions of Section B-2908.3] plumbing code.
* * *
B-3312.3 Pedestrian walkways: Construction materials and
equipment shall not be stored on the street without [a permit issued by the
administrative authority having jurisdiction] approval of the Streets
Department. Where so stored, such materials or equipment shall not unduly
interfere with vehicular traffic or the orderly travel of pedestrians on the
highway or street. The piles shall be arranged to maintain a safe walkway not
less than 4 feet (1219 mm) wide, unobstructed for its full length, and
adequately lighted at night and at all necessary times for the use of the
public.
* * *