In order to ensure that asbestos work is properly
performed so as to protect occupants of buildings and private residences and the
general public from exposure to asbestos, permits shall be required for all
major asbestos projects and notification shall be required prior to the
commencement of all minor asbestos projects.
(1) No contractor or other
person shall commence a major asbestos project unless he/she has obtained a
permit for that project from the Department of Licenses and
Inspections.
(2) Reserved.
[40] (3) Project
permit fees shall be based on the estimated cost of the asbestos abatement
portion of the project but shall be no less than two (2%) percent of the first
fifty thousand ($50,000) dollars and an additional one (1%) percent of any
amount over fifty thousand ($50,000) dollars. The minimum fee shall be one
hundred ($100) dollars.
(4) The Board shall establish by regulation the
requirements for obtaining a permit which shall include, but not be limited
to:
(a) possession of a valid license or, if the applicant is not an
asbestos contractor, certification by the Department of Licenses and
Inspections;
(b) use of certified asbestos workers;
(c) use of
appropriate equipment and materials.
(5) Permit applications shall
include, but shall not be limited to, the following
information:
(a) name and address of contractor or other person
responsible for the asbestos project;
(b) name and address of
independent certified asbestos project inspector;
(c) name and address
of independent certified laboratory;
(d) name and address of asbestos
waste transporter;
(e) name and address of asbestos waste disposal
facility;
(f) name and address of building owner;
(g) location
and function of building;
(h) description of asbestos project,
including amount and location of asbestos materials;
(i) description of
procedures and equipment that will be used to comply with the asbestos project
standards established by this Chapter, including any alternative equivalent
methods proposed for work area preparation;
(j) estimated total cost of
the project;
(k) scheduled starting and completion
dates.
(6) The Department of Licenses and Inspections shall not issue a
permit unless and until the Department has certified, in writing, that the
applicant has met the requirements established by the Board. In addition, the
Department of Licenses and Inspections shall impose upon a permit such terms and
conditions as the Department deems necessary to ensure compliance with the
provisions of this Chapter or regulations promulgated
thereunder.
(7) After a permit has been issued, the applicant shall
notify the Department, in advance, of any changes in the asbestos project not
accounted for in the permit application and submit an amended permit application
before project completion.
(8) The Department of Licenses and
Inspections, upon a finding by the Department that a person has failed to comply
with the provisions of this Chapter or regulations promulgated thereunder shall
deny, suspend, or revoke a permit in accordance with the recommendation of the
Department.
(9) Any action taken by the Department of Licenses and
Inspections pursuant to Section 6-603 may be appealed to the Board of License
and Inspection Review in accordance with its procedures.
(10) Minor
Asbestos Project
Notification.
[41] (a) No contractor or
other person shall commence a minor asbestos project unless he/she has notified
the Department in accordance with regulations established by the Board at least
twenty-four (24) hours prior to the commencement of the project.